What size, and what it costs.

A chiller that is forty per cent undersized does not hold the reservoir forty per cent less well. It holds it at 27 °C all summer, which is not a degraded outcome — it is root disease. So the sizing is arithmetic from stated assumptions rather than a rule of thumb, and every assumption is on the page where you can disagree with it.

Reservoir
200 L
Circulation
600 L/h
Peak delivery
26 L/h
Daily water
48 L
Chiller
161 W ≈ 0.22 HP
Aeration
1.7 L/min

Of that cooling load, 99 W leaks in through the tank wall and 30 W is the circulation pump putting its own power straight into the water — which is not a rounding error and is the figure most often left out. It pulls the tank down one degree in about 86.7 minutes, which is what decides whether it can recover from an afternoon.

The bill of materials

Bench Farm Commercial

One to five rooms, several zones. Raspberry Pi 5 running an-hydrod. 2 to 15 ESP32-S3. I²C sensors, RS-485 to industrial probes, MQTT smart plugs.

Survives a power cut, a router reboot and a monsoon week without anybody driving out to it.

Item Qty Each Line
Raspberry Pi 5, 8 GB, with SSD and case
SD cards fail. Use an SSD
1 ₹9,500 ₹9,500
UPS for the hub and the network 1 ₹4,500 ₹4,500
ESP32-S3 node, built as the Bench list
Per node, complete
4 ₹11,350 ₹45,400
RS-485 EC/pH/temperature transmitter
Industrial, and the redundancy that gives dosing authority
2 ₹7,800 ₹15,600
Substrate water content / EC sensor
Imported. Without this there is no crop steering
2 ₹12,500 ₹25,000
PAR sensor
Imported. Turns clock irrigation into light irrigation
1 ₹6,500 ₹6,500
Dissolved oxygen probe
Imported
1 ₹9,500 ₹9,500
Peristaltic dosing pumps, 24 V
pH-down, pH-up, A and B
4 ₹2,600 ₹10,400
Reservoir chiller, 1/4 HP
The item most often skipped and most often the reason a summer crop fails
1 ₹34,000 ₹34,000
Managed switch and outdoor-rated cabling 1 ₹6,000 ₹6,000
Distribution board, RCD, contactors
To be signed off by a licensed electrical engineer
1 ₹8,500 ₹8,500
Total, ex-GST₹174,900

Mid-2026 street prices for the Indian market. They will be wrong within a year and they are here anyway, because a bill of materials with no numbers in it is one nobody can make a decision from. Anything imported carries customs and freight that are frequently more than the part.

Electrical safety is not a line item. The RCD is in the list because it is mandatory, and the panel work at the Farm and Commercial tiers is engineered rather than assembled. Have the mains section reviewed by a licensed electrical engineer before anything is sold or installed.

Crop intelligence

Going in during August

Sowing windows open right now, from the crop reference.

Crop Sow Days pH Temp °C Yield
Guava Jul–Aug (planting) 2–3 yr to bear 6.0–7.5 23–30 20–25 t
Pomegranate Jul–Aug (planting) 2–3 yr to bear 6.5–7.5 20–35 15–20 t
Ber (Indian Jujube) Jul–Aug (planting) 2–3 yr to bear 6.0–8.5 20–35 15–20 t
Calamondin Jul–Aug 2–3 yr 5.5–6.5 18–32 12–20 t
Tea Jun–Aug (planting) 3–4 yr to pluck 4.5–5.5 18–30 2–3 t made tea
Oil Palm Jun–Sep (planting) 3–4 yr to bear 5.0–7.0 24–32 20–25 t FFB
Lemon Jul–Aug (planting) 3–4 yr to bear 6.0–7.5 20–32 15–20 t
Jojoba Jul–Aug 3–4 yr 6.0–8.0 20–35 1.5–3 t
Feijoa Jul–Aug 3–4 yr 5.5–7.0 10–25 10–15 t
Loquat Jul–Aug 3–4 yr 6.0–7.5 15–30 10–15 t
Jujube Jul–Aug 3–4 yr 6.0–8.0 15–35 10–15 t
Grapefruit Jul–Aug 3–4 yr 5.5–7.5 15–35 20–30 t
Citron Jul–Aug 3–4 yr 5.5–7.5 18–32 15–25 t
Kumquat Jul–Aug 3–4 yr 5.5–6.5 12–30 8–14 t

54 more in this list. All 538 crops, with every column → The sowing year →